Our CaseStudy
Tapi old bridge
METHODOLOGY FOR REPAIR
Bituminous wearing coat and R.C.C wearing coat were removed by jack hammer using compressed air
All plates put on expansion joints were removed
Study of damaged portion at the point of expansion joints and cross girders were carried out
Old cross girders were replaced by putting new cross girders with steel and concrete insitu
Broken portion of slab was recasted after welding extra Re-Bar as per design
Designed expansion joints, finger type were installed as per specifications
Hanging platform for scaffold work was erected from the top of the slab
Removal of leached, spalled, honey combed concrete surface was done manually and by Mechanical chippers
Surface preparation was done by wire brushing and applying bond coat of Polymer Modified Cement (PMC) slurry along with coating of Re-Bar with PMC bond Coat
Extra steel Re-Bar was added to original Re-Bar whose diameter was below 80% of original diameter and were coated by PMC slurry bond coat
PMC mortar was applied to fill hollows and cavities manually with Masons and finished to match the existing surface
For repairing cracks V-Groove was made by mechanical cutter and filled with Epoxy mortar
And then wholes of 200mm depth were drilled at a distance of 300mm on both sides of the girder
With help of nipples low viscosity Epoxy Grout was grouted from top of the slab with compressed air and Epoxy pump
Existing damaged R.C.C parapet was repaired using Polymer Modified Cement (PMC) Mortar
Profile corrective course of PCC was laid on the top of the slab
Water spout were fitted as per site requirement
Bituminous mecadum leveling course was laid on the top and bridge was opened for traffic